- Daily Field Report Report ID: 59909
- Edit Download Report
Daily Field Report
Date :06/22/2023
Project No :2022C106
Client Company :CWM
Arrival Time :06/22/2023 9:00
Onsite Hours :10:00
Name of the Project :Taxiway 2022 Pavement Replacement
Project Location :HJAIA
Weather :cloudy
Departure Time :06/22/2023 19:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to observe the contractor’s work activities from a quality standpoint to assure compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site this shift:
- A pre-pour observation was performed in the taxiway, phase 1A, Lane 1 and Lane 3 portions of the project this day. The contractor completed rebar and dowel basket placement for these lanes.
- The writer visually inspected the installation and setup of these lanes and advised the contractor representatives of any minor corrections that were required.
- Contractor cleaned loose rock and debris and puddles of water from the base.
- Baskets were found to be level and straight and secured.
- Dowel bars have epoxy. Embedment depth was found to be 15″ in concrete.
- Our representative along with Jose of ATLQA and the ATLNext representative Bralin and CWM rep Brandon signed the pre-pour card.
- Placement of LS concrete will occur at locations. lane1, STA 534+00 (7’x3.5′), Liane 1, STA 533+75 (4’x4′) and lane 1(STA 534+25 to STA 535+25).
- The sewer enhancement project was canceled due to the onset of inclement weather.
Technician Signature / DateAminullah Azimi, June 22, 2023
Reviewer Name / DateKenneth Mosman, July 09, 2023