Daily Field Report
Date :06/21/2023
Project No :2022C106
Client Company :CWM
Arrival Time :06/21/2023 14:00
Onsite Hours :04:00
Name of the Project :Taxiway 2022 Pavement Replacement
Project Location :HJAIA
Weather :rainy
Departure Time :06/21/2023 18:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to observe and monitor the contractor’s work activities from a quality standpoint to assure compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site this shift:
- A pre-pour observation performed in the taxiway, phase 1A, Lane 6 and Lane 8 portions of the project this day. The contractor completed rebar and dowel basket placement for these lanes.
- The writer visually inspected the installation and setup of these lanes and advised the contractor representatives of any minor corrections that were required.
- Contractor cleaned out loose rock.
- Baskets were found to be level and straight and secured.
- Dowel bars have epoxy. Embedment depth was found to be 15″ in concrete.
- Our representative along with Depto of ATLQA and the ATLNext representative Cornell did not sign the pre-pour card because in the north end, lane 8 displayed water ponding which the contractor could not remove due to inclement weather. The ATL Next rep moved the pre-pour card signature to the night shift.
Technician Signature / DateAminullah Azimi, June 21, 2023
Reviewer Name / DateKenneth Mosman, July 09, 2023