- Home
- Daily Field Report Report ID: 59847
- This project is inactive from admin.Download Report
Daily Field Report
Date :06/20/2023
Project No :2022C235
Client Company :Jackson Demolition Service, Inc.
Arrival Time :06/20/2023 06:00
Onsite Hours :10:30
Name of the Project :Plant Gorgas Demolition and Grading
Project Location :460 Gorgas Rd, Parrish, AL 35580
Weather :PARTLY CLOUDY
Departure Time :06/20/2023 16:30
ASEC Technician Name :Avinash Bandham
Observations/Finding
AS ENGINEERING AND CONSULTING, LLC (ASEC) representative Avinash Bandam visited the site at the request of Jackson Demolition representative Josh Kelly. The undersigned representative was present to monitor, verify and document the ongoing project activities. (reference drawing E720661 S1 – R8, E720659 S1-R8.)
During the visit, the following observations were made:
- One thousand five hundred and forty-eight (1548) cubic yards of fill materials were placed for lift (14) in section 2 part 2 area G7 (E720659 S1-R8) of the basement and completed the lift and the new lift in the Section 1 basement area G7 (E720661 S1 – R8). The materials were placed and compacted in accordance with ITP-001, and the fill area is highlighted in brown as depicted in the attached drawing.
- The area was probed with a hand probe and three moisture density nuclear gauge tests were performed in the basement, section 1 and section 2 and verified the results by running a check-plug. The test locations are depicted in the enclosed drawing.
Technician Signature / DateAvinash Bandham, June 20, 2023
Reviewer Name / DateRamchandra Mogulla, June 28, 2023