Skip to content

Daily Field Report

Date :06/17/2023
Project No :2022C235
Client Company :Jackson Demolition Service, Inc.
Arrival Time :06/17/2023 06:00
Onsite Hours :10:30
Name of the Project :Plant Gorgas Demolition and Grading
Project Location :460 Gorgas Rd, Parrish, AL 35580
Weather :SUNNY
Departure Time :06/17/2023 16:30
ASEC Technician Name :Avinash Bandham

Observations/Finding

AS ENGINEERING AND CONSULTING, LLC (ASEC) representative Avinash Bandam visited the site at the request of Jackson Demolition representative Josh Kelly. The undersigned representative was present to monitor, verify and document the ongoing project activities. (reference drawing E720661 S1 – R8, E720659 S1-R8.)

During the visit, the following observations were made:

  1. One thousand and nighty-eight (1098) cubic yards of fill materials were placed for lift (14) in section 2 area G7 (drawing E720659) of the basement. The materials were placed and compacted in accordance with ITP-001, and the approximate fill area is highlighted in brown as depicted in the attached drawing.

Technician Signature / DateAvinash Bandham, June 17, 2023
Reviewer Name / DateRamchandra Mogulla, June 28, 2023