Daily Field Report

Date :05/15/2023
Project No :2022C178
Client Company :CW Matthews
Arrival Time :05/15/2023 8:00
Onsite Hours :08:00
Name of the Project :Ramp 2 Pavement Replacement
Project Location :HJAIA
Weather :rainy
Departure Time :05/15/2023 16:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

At the request of the client’s representative, AS ENGINEERING AND CONSULTING, LLC (ASEC) representative, Amin Azimi visited the job site to observe and monitor the contractor’s work activities from a quality standpoint to assure compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications.  The following observations were made on site this shift:

  • Work was being performed in the Ramp 2 – Phase 4 and sewer enhancements of the project on this day.
  • Performed concrete coring and filling and logger reading for Ramp 2 – Phase 4.
  • Our representative, along with Depto of ATLQA and ATLNext representative Hazim and CWM rep Brandon observed the process.
  • In addition, our ASEC representative observed straight edge testing of Ramp 2 – Phase 4.
  • Also observed the installation of pipe between MH#3 and MH#9 and contractor installation of MH#3.  GAB compaction was not ready for testing today.

 

Technician Signature / DateAminullah Azimi, May 15, 2023
Reviewer Name / DateKenneth Mosman, July 08, 2023