Density Test Report

Date :03/15/2023
Project No :2022C136
Client Company :Century
Arrival Time :03/15/2023 15:30
Onsite Hours :02:30
Name of the Project :Logan Pointe
Project Location :Loganville
Weather :Sunny
Departure Time :03/15/2023 18:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
03/15/2023 1 24.2 98.9 P-1 99.0 21.4 99.9 90 D6938 Pass
Location : Lot #56, Elv/Depth :at finished grade
Comment : Gauge Serial No. :85759
03/15/2023 2 22.3 100.2 P-1 99.0 21.4 101.2 90 D6938 Pass
Location : Lot #56, Elv/Depth :at finished grade
Comment : Gauge Serial No. :85759
03/15/2023 3 24.7 92.5 P-1 99.0 21.4 93.4 90 D6938 Pass
Location : Lot #66, Elv/Depth :at finished grade
Comment : Gauge Serial No. :85759
03/15/2023 4 24.1 96.9 P-1 99.0 21.4 97.9 90 D6938 Pass
Location : Lot #65, Elv/Depth :at finished grade
Comment : Gauge Serial No. :85759
Technician Signature / DateAminullah Azimi, March 15, 2023
Reviewer Name / DateKenneth Mosman, April 02, 2023