Skip to content

Daily Field Report

Date :03/09/2023
Project No :2022C182
Client Company :Excellere
Arrival Time :03/09/2023 08:00
Onsite Hours :04:00
Name of the Project :Eastside Trolley Trail
Project Location :Atlanta
Weather :Rainy
Departure Time :03/09/2023 12:00
ASEC Technician Name :Isaac Davis

Observations/Finding

As requested, our AS Engineering & Consulting (ASEC) representative was on site to observe concrete placement and sample fresh concrete placed for the first half of the sidewalks located between Sta 34+00 and 35+00.  See attached photos taken during the placement.  Results of sampling are attached in a separate report.

Technician Signature / DateIsaac Davis, March 9, 2023
Reviewer Name / DateKenneth Mosman, March 13, 2023