- Home
- Daily Field Report Report ID: 57455
- This project is inactive from admin.Download Report
Daily Field Report
Date :01/26/2023
Project No :2022C174
Client Company :CWM
Arrival Time :01/26/2023
Onsite Hours :
Name of the Project :CWM Plant on Mulberry Rock Road
Project Location :Dallas, Paulding County
Weather :Cloudy
Departure Time :01/26/2023
ASEC Technician Name :Russell Hendrix
Observations/Finding
As requested, our ASEC representative was on site to observe concrete placement for one of the structure slabs placed today. One (1) set of four (4) concrete test specimens were cast. See attached concrete sampling report for results of testing.
Technician Signature / DateKenneth Mosman, January 26, 2023
Reviewer Name / DateRamchandra Mogulla, May 29, 2023