Density Test Report

Date :12/19/2022
Project No :2022C136
Client Company :Century
Arrival Time :12/19/2022 9:00
Onsite Hours :08:00
Name of the Project :Logan Pointe
Project Location :Loganville
Weather :cloudy
Departure Time :12/19/2022 17:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
12/19/2022 1 32 83.3 P-3 96.5 22.2 86.3 90 D6938 Fail
Location : Lot #66, Elv/Depth :-1 foot from finish grade
Comment : the moisture content was well above optimum moisture content Gauge Serial No. :85759
12/19/2022 2 31 85.7 P-3 96.5 22.2 88.8 90 D6938 Fail
Location : Lot #64, Elv/Depth :-2 feet from finish grade
Comment : the moisture content was well above optimum moisture content Gauge Serial No. :85759
Technician Signature / DateAminullah Azimi, December 19, 2022
Reviewer Name / DateKenneth Mosman, January 16, 2023