Daily Field Report

Date :05/25/2022
Project No :2022C128
Client Company :Century
Arrival Time :05/25/2022 08:00
Onsite Hours :05:00
Name of the Project :Sidney Square, Flowery Branch
Project Location :Flowery Branch
Weather :
Departure Time :05/25/2022 13:00
ASEC Technician Name :Rasheen Biggins

Observations/Finding

The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today.

Upon arrival to the project site, our ASEC representative observed that work was already in progress. Contractors were performing lift placements of approximately 8 to 10 inches in thickness. Density test results were found to be just under required compaction and were reported to the contractor.  Mr. Ram Mogulla P.E. of ASEC advised that a change in material may have been encountered and to allow the contractor to continue fill placement.

Technician Signature / DateRasheen Biggins, May 25, 2022
Reviewer Name / DateKenneth Mosman, November 13, 2022