Daily Field Report

Date :04/27/2022
Project No :2022C128
Client Company :Century
Arrival Time :04/27/2022 09:00
Onsite Hours :08:00
Name of the Project :Sidney Square, Flowery Branch
Project Location :Flowery Branch
Weather :
Departure Time :04/27/2022 17:00
ASEC Technician Name :Rasheen Biggins

Observations/Finding

The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today.

Upon arrival our ASEC representative found work in progress. Mr. Ram Mogulla P.E. of ASEC recommended that the contractor remove 1-1/2 foot of soft grey soil from the shoulder/lot area (this area was located 20 feet east of wall). The contractor was advised that the first backfill lift should be placed approximately  18 inches in depth. Soil was spread by a bulldozer Komatsu 61px and compacted with a sheeps-foot compactor. Density tests were then taken following the placement of each lift.

Technician Signature / DateRasheen Biggins, April 27, 2022
Reviewer Name / DateKenneth Mosman, November 13, 2022