- Home
- Daily Field Report Report ID: 54019
- This project is inactive from admin.Download Report
Daily Field Report
Observations/Finding
The site was visited by Rasheen Biggins AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today.
Upon arrival to the project site, our representative observed work was already in progress. The contractor was continuing to place fill in the dam area and along the adjacent pipeline. A CAT excavator spread fill materials brought by one CAT Dump truck which were compacted using a Wacker packer and Wacker Neusen RT trench roller compactor. Density tests were performed on the fill placed. Based on the density test results, visual observation of the material placed and random probing of the placed lifts, the fill placed was found to meet job specifications for soil compaction. Density tests were taken with Troxler gauge #38069 and the results were reported back to the contractor. Test results can be found in the attached density report.