Daily Field Report
Observations/Finding
The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawings/specifications, applicable codes, and materials submittals.
The ASEC representative performed Dynamic Cone Penetrometer (DCP) tests one the below referenced footing areas. All referenced footings were found to meet job specification for a soil bearing pressure of 2,500 psf.
A reinforcing steel inspection was performed on the following locations: (Lots #6, 7, and 41). Reinforcing steel was observed to meet job specifications for required size, spacing, lap and cover. No discrepancies were noted.
If foundation soils become wet prior to concrete placement, they should be reevaluated by a geotechnical engineer or qualified soils technician. All loose fall-in soils or debris should be removed from foundations prior to concrete placement.
DCP TEST DATA SHEET | |||||||||||||
Project Name: | Suncity- Peachtree | Date: | January 25 | ||||||||||
Project Number: | 2021C060 | Technician: | Jamal Geathers | ||||||||||
Project Location: | Griffin, Ga | ||||||||||||
DCP LOCATION: Lot #, North/South/Center etc |
Lot 7 (Front of lot) | DCP LOCATION: Lot #, North/South/Center etc |
Lot 7 (back of lot) | ||||||||||
Depth (feet) |
Set 2″ |
N 1.75″ |
Description | Depth (feet) |
Set 2″ |
N 1.75″ |
Description | ||||||
1 | 9 | 11 | 1 | 8 | 11 | ||||||||
2 | 9 | 12 | 2 | 8 | 10 | ||||||||
3 | 9 | 10 | 3 | 8 | 9 | ||||||||
4 | 9 | 1o | 4 | 8 | 8 | ||||||||
5 | 5 | ||||||||||||
6 | 6 | ||||||||||||
7 | 7 | ||||||||||||
8 | 8 | ||||||||||||
9 | 9 | ||||||||||||
10 | 10 | ||||||||||||
jrg | |||||||||||||
DCP LOCATION: Lot #, North/South/Center etc |
Lot 6 (front of lot) | DCP LOCATION: Lot #, North/South/Center etc |
lot 10 back of lot | ||||||||||
Depth (feet) |
Set 2″ |
N 1.75″ |
Description | Depth (feet) |
Set 2″ |
N 1.75″ |
Description | ||||||
1 | 8 | 7 | 1 | 8 | 9 | ||||||||
2 | 8 | 11 | 2 | 8 | 12 | ||||||||
3 | 8 | 12 | 3 | 8 | 13 | ||||||||
4 | 8 | 18 | 4 | 8 | 12 | ||||||||
5 | 5 | ||||||||||||
6 | 6 | ||||||||||||
7 | 7 | ||||||||||||
8 | 8 | ||||||||||||
9 | 9 | ||||||||||||
10 | 10 |
DCP TEST DATA SHEET | ||||||||||||
Project Name: | Suncity- Peachtree | Date: | January 25 | |||||||||
Project Number: | 2021C060 | Technician: | Jamal Geathers | |||||||||
Project Location: | Griffin, Ga | |||||||||||
DCP LOCATION: Lot #, North/South/Center etc |
Lot 41 (left side of Lot) | DCP LOCATION: Lot #, North/South/Center etc |
Lot 41( Back of lot) | |||||||||
Depth (feet) |
Set 2″ |
N 1.75″ |
Description | Depth (feet) |
Set 2″ |
N 1.75″ |
Description | |||||
1 | 9 | 16 | 1 | 8 | 18 | |||||||
2 | 9 | 15 | 2 | 8 | 16 | |||||||
3 | 9 | auger refusal | 3 | 8 | 14 | |||||||
4 | 9 | 4 | 8 | 17 | ||||||||
5 | 5 | |||||||||||
6 | 6 |