- Daily Field Report Report ID: 52811
- Edit Download Report
Daily Field Report
Date :12/21/2021
Project No :2021C060
Client Company :Pulte Group
Arrival Time :12/06/2021 13:30
Onsite Hours :01:00
Name of the Project :Suncity - Peachtree
Project Location :Griffin, GA
Weather :cloudy
Departure Time :12/06/2021 14:30
ASEC Technician Name :Russell Hendrix
Observations/Finding
The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today:
A slab subgrade inspection request was made for Lot #7 in the “Pinnacle” section of the development. All rebar was installed to IBC requirements for size, spacing and quantity. The footing was probed and a DCP was completed and deemed suitable for concrete placement. Please see the attached data table.
DCP TEST DATA SHEET | ||||||||||||
Project Name: | Suncity | Date: | 12/06/21 | |||||||||
Project Number: | 2021c060 | Technician: | Russ Hendrix | |||||||||
Project Location: | Griffin | |||||||||||
DCP LOCATION: Lot #, North/South/Center etc |
DCP LOCATION: Lot #, North/South/Center etc |
|||||||||||
Depth (feet) |
Set 2″ |
N 1.75″ |
Description | Depth (feet) |
Set 2″ |
N 1.75″ |
Description | |||||
1 | 12 | Red silty fine sand | 1 | |||||||||
2 | 13 | Red silty fine sand | 2 | |||||||||
3 | 14 | Red silty fine sand | 3 | |||||||||
4 | 14 | Red silty fine sand | 4 | |||||||||
5 | 5 | |||||||||||
6 | 6 | |||||||||||
7 | 7 | |||||||||||
8 | 8 | |||||||||||
9 | 9 | |||||||||||
10 | 10 | |||||||||||
DCP LOCATION: Lot #, North/South/Center etc |
DCP LOCATION: Lot #, North/South/Center etc |
|||||||||||
Depth (feet) |
Set 2″ |
N 1.75″ |
Description | Depth (feet) |
Set 2″ |
N 1.75″ |
Description | |||||
1 | 1 | |||||||||||
2 | 2 | |||||||||||
3 | 3 | |||||||||||
4 | 4 | |||||||||||
5 | 5 | |||||||||||
6 | 6 | |||||||||||
7 | 7 | |||||||||||
8 | 8 | |||||||||||
9 | 9 | |||||||||||
10 | 10 | |||||||||||
NOTES: | ||||||||||||
Technician Signature / DateRussell Hendrix, December 21, 2021
Reviewer Name / DateKenneth Mosman, December 21, 2021