Skip to content

Daily Field Report

Date :11/17/2021
Project No :2021C074
Client Company :DR Horton West
Arrival Time :11/17/2021 14:00
Onsite Hours :03:15
Name of the Project :Oakhurst Glen - Ph 4
Project Location :Mallord Drive, South Fulton, GA
Weather :Partly Cloudy
Departure Time :11/17/2021 17:15
ASEC Technician Name :Christopher Burrow II

Observations/Finding

As requested, an ASEC Inspector was present at the above referenced site for the purpose of observing the placement of structural fill in the roadway areas behind lots 332 through 334 (area of 25 feet by 200 feet). Based on review of guidelines for fill placement, the required compaction for structural fill at the above mentioned area was 95 % of standard proctor. Based on visual observation and field measuring, the fill was placed in 8 to 12 inch thick lifts and compacted using a CAT 815F sheeps-foot compactor(weight; 45,757 lbs.). Based on density testing, the fill placed today at depths between approximately -1 feet and -0 feet below finished grade was compacted according to fill placement guidelines. See attached density test results for more details.

The undersigned ASEC Inspector was on site, on the above date, for the purpose of general site monitoring and assessment of contractor and subcontractor activities. The following are observations that were made at this time:

-Rock Breaking continued on site.

-Building fill slopes near entrance roadway.

-Continuing road drains in area of B1 and B1.1.

ASEC recommends sealing of the surface of placed fill from inclement weather and to maintain positive drainage.

The contractor was notified about results. 

Technician Signature / DateChristopher Burrow II, November 17, 2021
Reviewer Name / DateKenneth Mosman, December 06, 2021