- Home
- Daily Field Report Report ID: 33914
- This project is inactive from admin.Download Report
Daily Field Report
Observations/Finding
As requested, a ASEC Inspector was present at the above referenced site for the purpose of observing the placement of structural fill at the area of lots 346 through 347 and 291 through 292 approximate size 50 feet by 200 feet. Based on review of guidelines for fill placement, the required compaction for structural fill at the above mentioned area is 95 % of standard proctor. Fill was placed in 8 to 12 inch thick lifts and compacted using CAT 815F sheepsfoot compactor(weight; 45,757 lbs.).
Based on density testing, the fill placed today at elevations between approximately -6 feet and -5 feet below finished grade was compacted according to fill placement guidelines. See attached density test results for more details.
The undersigned ASEC Inspector was on site, on the above date, for the purpose of general site monitoring and assessment of contractor and subcontractor activities. The following are observations that were made at this time:
- Rock Breaking on site is continued.
- Removing piles of unsuitable soils on property and placing it in green areas and fill slopes.
ASEC recommends sealing of the surface of placed fill from inclement weather and maintain the positive drainage.
The contractor was notified about results.