Daily Field Report
Observations/Finding
The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today:
Upon arrival at project site excavation and installation of storm water drain between A5-A6 had begun. Approximately 50 feet of 16″ black corrugated pipe was installed with 5 inches of #57 stone under and to the sides. Soil was backfilled in 6″ lifts and compacted initially with a RTSC2 Wacker Nuesom. Final compaction was achieved with a BW211 PD-50. Please see attached photos.