Daily Field Report
Observations/Finding
The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today:
A rebar and footing inspection was scheduled for the subject properties listed as Lots 10, 11, 40 ,41, 42
The writer upon arrival to the site observed that only lot 42 was ready for inspection. The other lots (10,11,40,41) did not have footings or rebar in place.
Due to heavy rainfall the previous days lot 42 was heavily saturated, and would require “de-mucking” and re-cutting of the footings. The Rebar in place was found acceptable based on the following observations.
- Based on the rebar size (#4), placement (single row spaced at 6 inches apart) with 2” chairs. The rebar placement, Lap length and bar ties found acceptable according to specification.
- DCP tests was performed (see DCP test results) Based on the density test results, visual observation and random probing, the footings were found to be acceptable and within plan specifications, but would still need to be re-cut.
DCP Tests were also performed on lots 10,11,40 and 41. Based on the density test results, visual observation and random probing, the footings were found to be acceptable and within plan specifications. The density test report for this day list the test results for the work performed on this day.
Lot 42
Lot 40
Lot 41
Lot 11
Lot 10