Daily Field Report

Date :01/13/2025
Project No :2024C202
Client Company :CCG
Arrival Time :01/13/2025 07:30
Onsite Hours :02:30
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Partly cloudy
Departure Time :01/13/2025 10:00
ASEC Technician Name :Solomon Cherie

Observations/Finding

Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:

Upon arrival, our representative found the site to still be partially covered with the recent snow event.  Several spot moisture contents averaged approximately 32%.  Based on both conditions, the contractor elected not to perform grade work this day.

Please contact us if you have any questions regarding this report or of the density test results.

Picture showing still thick snow cover

Only patches of snow left after. melting melting

Technician Signature / DateSolomon Cherie, January 13, 2025
Reviewer Name / DateKenneth Mosman, January 14, 2025