Date :01/06/2025
Project No :2024C217
Client Company :Artisan
Arrival Time :01/06/2025 08:00
Onsite Hours :08:00
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :cloudy
Departure Time :01/06/2025 16:00
ASEC Technician Name :Vamsi Polisetty

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Seven Hills: Amenities:

Due to the excessive rainfall from the preceding days, the jobsite remained saturated.   The contractor elected to spend the day scarifying and aerating wet surficial soils by discing, spreading and aerating during the day.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you

Technician Signature / DateVamsi Polisetty, January 6, 2025
Reviewer Name / DateKenneth Mosman, January 13, 2025