Daily Field Report

Date :01/08/2025
Project No :2024C202
Client Company :CCG
Arrival Time :01/08/2025 07:30
Onsite Hours :08:45
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Clear sky
Departure Time :01/08/2025 16:15
ASEC Technician Name :Solomon Cherie

Observations/Finding

Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:

Observed the placement of fill/grading for Lots #27 through #30 today. Compaction tests were performed using a nuclear density gauge. Overall, the results of density testing confirmed that fill compaction met the project and ASTM requirements. Results are attached in separate reports.

An additional compaction test was performed on Lot #63.  Backfilling of the sewer line trench between Manhole A12 & A13 was completed today.  General probing found the subgrade soils stable.

Please contact us if you have any questions regarding this report or of the density test results.

 

 

Picture depicting 12-50 feet backfill building pads

Sewer line backfilled and compacted

Sewer line trench before complete backfill and compaction

Technician Signature / DateSolomon Cherie, January 8, 2025
Reviewer Name / DateKenneth Mosman, January 10, 2025