Daily Field Report
Date :01/03/2025
Project No :2024C202
Client Company :CCG
Arrival Time :01/03/2025 07:45
Onsite Hours :
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Partly cloudy
Departure Time :01/03/2025
ASEC Technician Name :Solomon Cherie
Observations/Finding
Down cutting and back filling activities were carried out during the day.
The down cutting was from a nearby road cut area and was done using 349E CAT excavator whereas hauling by two 745C heavy duity dam trucks.
The hauled dirt was spread by the 61Pxi Komatsu bulldozer and the compaction was done by the 815F CAT roller.
The building pads were Lots 62 and 63 which is about 9.00 feet back fill. The total area of back fill was about
Technician Signature / DateSolomon Cherie, January 3, 2025
Reviewer Name / DateKenneth Mosman, January 10, 2025