Daily Field Report

Date :12/21/2024
Project No :2024C217
Client Company :Artisan
Arrival Time :12/21/2024 08:00
Onsite Hours :08:00
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :sunny
Departure Time :12/21/2024 16:00
ASEC Technician Name :Vamsi Polisetty

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Savannah Pipeline Company has commenced leveling the excavated pipeline work from previous days using a Kobelco SK350LC excavator. the slopes are levelled. Dozed and graded with a Deere 650K dozer. These tasks have been executed with precision by the team, and additional work is scheduled for the following day to maintain steady progress on the project.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you

Technician Signature / DateVamsi Polisetty, December 21, 2024