Skip to content

Concrete Test Report

Date :12/20/2024
Project No :2024C202
Client Company :CCG
Arrival Time :12/20/2024 07:30
Onsite Hours :
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Sunny
Departure Time :12/20/2024
ASEC Technician Name :Solomon Cherie

Concrete Placement Information

Location(S):
Testing: 1 Set of concrete specimens (7 Cylinders per set) were cast during the cast-in-place concrete pour at the above referenced location, in accordance with ASTM C31. The cylinders will remain on site for the initial 24-48 hrs curing.
Compliance:

Field placement of concrete appeared to be in accordance with the project specifications (i.e., slump, temperature, etc) (refer to remarks below)

Deviations and/or noncompliances were noted during the field placement (refer to remarks below)

Cylinders
Pick Up:
1 Sets of concrete cylinders/ 7 cylinders per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Field Curing: Cylinders were stored for the initial 24 hours
Near the poured structure
In an insulated curing box
Other
Remarks: Totally 57 yards of concrete was poured and one set of seven cylinders were casted. There was long hours waiting time while concur trucks are coming. Hence pouring took extended time.
Technician Signature / DateSolomon Cherie, December 20, 2024