Daily Field Report

Date :10/15/2024
Project No :2024C217
Client Company :Artisan
Arrival Time :10/15/2024 08:03
Onsite Hours :9:15
Name of the Project :Naturewalk - 7 Hills Amenities
Project Location :Dallas
Weather :sunny
Departure Time :10/15/2024 17:15
ASEC Technician Name :Vamsi Polisetty

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

  • Upon arrival, the contractor was engaged in excavation using a Komatsu PC 360LC to the west of the project site. . Dirt was being transported with two tandem dump trucks near the Pickle Ball Court, while dozing and leveling were performed with a Komatsu D85EX.
  • Boulders are used in backfilling under the tennis court and Pickle Ball court, necessary instructions like proof rolling are made for the proper compaction.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you

Technician Signature / DateVamsi Polisetty, October 15, 2024