Concrete Test Report

Date :10/14/2024
Project No :2024C223
Client Company :CWM
Arrival Time : 16:00
Onsite Hours :06:30
Name of the Project :Concourse E Gate & Ramp 6 North Gate
Project Location :HJAIA
Weather :
Departure Time : 22:30
ASEC Technician Name :

Concrete Placement Information

Location(S):
Testing: 1 Set of concrete specimens (11 Cylinders per set) were cast during the cast-in-place concrete pour at the above referenced location, in accordance with ASTM C31. The cylinders will remain on site for the initial 24-48 hrs curing.
Compliance:

Field placement of concrete appeared to be in accordance with the project specifications (i.e., slump, temperature, etc) (refer to remarks below)

Deviations and/or noncompliances were noted during the field placement (refer to remarks below)

Cylinders
Pick Up:
1 Sets of concrete cylinders/ 11 cylinders per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Field Curing: Cylinders were stored for the initial 24 hours
Near the poured structure
In an insulated curing box
Other
Remarks: One set of eleven (11) beams were cast.
Technician Signature / DateSolomon Cherie, October 14, 2024
Reviewer Name / DateKenneth Mosman, October 20, 2024