- Daily Field Report Report ID: 70894
- Edit Download Report
Daily Field Report
Date :10/04/2024
Project No :2024C195
Client Company :CWM
Arrival Time :10/04/2024 12:30
Onsite Hours :02:45
Name of the Project :Ramp 21 Replacement
Project Location :HJAIA
Weather :
Departure Time :10/04/2024 15:15
ASEC Technician Name :Solomon Cherie
Observations/Finding
As requested, our AS Engineering & Consulting LLC representative was on site to observe concrete placement. The following were performed this day:
1) Air content tests, concrete temperature, slump and unit weight were taken for Truck #1 and Truck #3 sampled.
2) One set of seven (7) beams were cast.
All concrete tests were found to be within job specifications.
One set of 7 beams
Technician Signature / DateSolomon Cherie, October 4, 2024
Reviewer Name / DateKenneth Mosman, October 20, 2024