Daily Field Report
Date :09/14/2024
Project No :2024C168
Client Company :CCG
Arrival Time :09/14/2024 8:30
Onsite Hours :07:00
Name of the Project :Reserve @ Gum Springs
Project Location :Jefferson
Weather :rainy
Departure Time :09/14/2024 15:30
ASEC Technician Name :Aminullah Azimi
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
- The placement and compaction of fill soils for the storm water trench between, MH6.8.1, MHB6.8.2, MHB6.10, MHB6.10.1 and MHB6.10.2, and installing water lines in the front of Lots #163 to #165, continued this day.
- At the time of arrival, our representative observed that work was in progress with1-foot lifts being placed and compacted using CP56B and trench compaction equipment. Compaction testing was performed along with general probing using a 3/8″ diameter probe rod.
- Note: due to the onset of rain, density testing could not be performed.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.
Technician Signature / DateAminullah Azimi, September 14, 2024
Reviewer Name / DateKenneth Mosman, October 20, 2024