- Density Test Report Report ID: 69865
- Edit Download Report
Density Test Report
Date :09/11/2024
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :09/11/2024 08:00
Onsite Hours :
Name of the Project :Lakeside Sub. - Lovers Lane, Calhoun
Project Location :Calhoun
Weather :
Departure Time :09/11/2024
ASEC Technician Name :
Observations/Finding
Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
---|---|---|---|---|---|---|---|---|---|---|
09/11/2024 | Test 6 | 12.9 | 95.6 | P-01 | 97.0 | 19.1 | 98.6 | 95 | D6938 | Pass |
Location : | Lot number 125-131, Elv/Depth :-1.0' | |||||||||
Comment : | Compaction is greater than 95%, which isthe minimum percentage. | Gauge Serial No. :30942 | ||||||||
Check | ||||||||||
Location : | , Elv/Depth : | |||||||||
Comment : |
Technician Signature / DateSolomon Cherie, September 11, 2024