Daily Field Report

Date :08/22/2024
Project No :2024C195
Client Company :CWM
Arrival Time :08/22/2024 18:00
Onsite Hours :04:30
Name of the Project :Ramp 21 Replacement
Project Location :HJAIA
Weather :Clear sky
Departure Time :08/22/2024 22:30
ASEC Technician Name :Solomon Cherie

Observations/Finding

Upon arrival we did,

1) Moisture tests,

2) Strip two sets of each seven beams,

3) Conduct air, slump, temperature and unit weight tests for the first truck,

4) Conduct the same test in item number 3 and casted one set of seven beams for truck number 23,

5) Clean all equipment and working area and arrange everything in order.

 

Technician Signature / DateSolomon Cherie, August 22, 2024