Daily Field Report

Date :08/13/2024
Project No :2024C168
Client Company :CCG
Arrival Time :08/13/2024 14:30
Onsite Hours :04:30
Name of the Project :Reserve @ Gum Springs
Project Location :Jefferson
Weather :sunny
Departure Time :08/13/2024 19:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

  • The placement and compaction of fill for Lots #98, 99, 100, 101, 102, 103, 104, 105, 106, 130, 131, 132, the sewer trench between MH A10 and C1, the sewer trench between C1, C2 and C3 and water storm between MH A2 to MH A2.3, continued this day.
  • At the time of arrival, our representative observed that work was in progress with 1-foot lifts being placed and compacted using 815F, trench compactor and CP56B compaction equipment. Compaction testing was performed using a Troxler nuclear density gauge, along with general probing using a 3/8″ diameter probe rod.
  • Density test results indicate that the compacted materials met the project requirement of 95% of a maximum dry density obtained by a Standard Proctor ASTM 698. 

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateAminullah Azimi, August 13, 2024
Reviewer Name / DateKenneth Mosman, August 17, 2024