Concrete Test Report

Date :07/31/2024
Project No :2024C195
Client Company :CWM
Arrival Time :07/30/2024 20:00
Onsite Hours :07:45
Name of the Project :Ramp 21 Replacement
Project Location :HJAIA
Weather :Cloudy
Departure Time :07/31/2024 03:45
ASEC Technician Name :Solomon Cherie

Concrete Placement Information

Location(S):
Testing: 1 Set of concrete specimens (7 Cylinders per set) were cast during the cast-in-place concrete pour at the above referenced location, in accordance with ASTM C31. The cylinders will remain on site for the initial 24-48 hrs curing.
Compliance:

Field placement of concrete appeared to be in accordance with the project specifications (i.e., slump, temperature, etc) (refer to remarks below)

Deviations and/or noncompliances were noted during the field placement (refer to remarks below)

Cylinders
Pick Up:
1 Sets of concrete cylinders/ 7 cylinders per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Field Curing: Cylinders were stored for the initial 24 hours
Near the poured structure
In an insulated curing box
Other
Remarks: Air content, concrete temperature, slump and unit weight tests were performed and found to meet job specifications. One (1) set of seven beams were cast.
Technician Signature / DateSolomon Cherie, July 31, 2024
Reviewer Name / DateKenneth Mosman, August 06, 2024