Daily Field Report

Date :06/20/2024
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :06/20/2024 07:30
Onsite Hours :10:00
Name of the Project :Lakeside Sub. - Lovers Lane, Calhoun
Project Location :Calhoun
Weather :Sunny
Departure Time :06/20/2024 17:30
ASEC Technician Name :Marteze Jeter

Observations/Finding

At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to observe the contractor’s work activities from a quality standpoint to verify compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications.  The following observations were made on site this shift:

Our representative observed the contractor use CAT 336 equipment to excavate and transport backfill. A CAT 3314 was used to excavate a trench and lay 160ft sanitary sewer laterals from MH 1.5 – 1.6.  A CAT 938K loader was used to transport No. 57 stone and GAB.  No. 57 stone was placed up to 6 inches above the sanitary sewer lateral.  GAB and backfill was then added from MH 1.5 – 1.6 and compacted using a walk behind roller.

Our representative observed a SY365LC excavator dig a trench from MH 6.9 – 6.11 (205.3 + 34.7+ 32 + 153.2).

Observations:

  1. Backfilling Activities:   Contractors placed backfill in sewer laterals and storm trenches. Also added 6 inches of No. 57 stone, then a GAB.
  2. Storm Drainpipe Installation:  Contractors inserted sewer laterals.

Conclusion: The ongoing backfilling and storm drainpipe installation activities are progressing as planned.

Technician Signature / DateMarteze Jeter, June 20, 2024
Reviewer Name / DateKenneth Mosman, July 22, 2024