Density Test Report

Date :05/02/2024
Project No :2024C112
Client Company :SR Homes
Arrival Time :05/02/2024 9:00
Onsite Hours :9:00
Name of the Project :Sterlington
Project Location :Canton
Weather :sunny
Departure Time :05/02/2024 18:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
05/02/2024 1 28.2 90.2 P-01 94.8 25.0 95.1 95 D6938 Pass
Location : STA 1+32.00, Elv/Depth :7 feet from top of wall
Comment : Gauge Serial No. :38069
05/02/2024 2 27.8 90.2 P-01 94.8 25.0 95.1 95 D6938 Pass
Location : STA 0+66.75, Elv/Depth :11 feet from top of wall
Comment : Gauge Serial No. :38069
05/02/2024 3 27.3 90.6 P-01 94.8 25.0 95.6 95 D6938 Pass
Location : STA 0+28.50, Elv/Depth :7 feet from top of wall
Comment : Gauge Serial No. :38069
05/02/2024 4 28 90.2 P-01 94.8 25.0 95.1 95 D6938 Pass
Location : STA 0+54.75, Elv/Depth :9 feet from top of wall
Comment : Gauge Serial No. :38069
05/02/2024 5 27.1 90.2 P-01 94.8 25.0 95.1 95 D6938 Pass
Location : STA 0+81.75, Elv/Depth :9 feet from top of wall
Comment : Gauge Serial No. :38069
05/02/2024 6 26.5 90.1 P-01 94.8 25.0 95.0 95 D6938 Fail
Location : STA 1+08.00, Elv/Depth :8 feet below from top of wall
Comment : Gauge Serial No. :38069
Technician Signature / DateAminullah Azimi, May 2, 2024
Reviewer Name / DateKenneth Mosman, July 10, 2024