Density Test Report

Date :05/21/2024
Project No :2022C106
Client Company :CWM
Arrival Time :05/21/2024 11:00
Onsite Hours :04:00
Name of the Project :Taxiway 2022 Pavement Replacement
Project Location :HJAIA
Weather :sunny
Departure Time :05/21/2024 15:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
05/21/2024 1 4 132.0 GAB 1 135.6 6.8 97.3 95 D6938 Pass
Location : Shoulder of NLVR, N: 9278.6 E: 138525., Elv/Depth :finished grade
Comment : Gauge Serial No. :38069
05/21/2024 2 3.8 131.4 GAB 1 135.6 6.8 96.9 95 D6938 Pass
Location : Shoulder of NLVR, N: 9279.4 E: 13785.2, Elv/Depth :finished grade
Comment : Gauge Serial No. :38069
Technician Signature / DateAminullah Azimi, May 21, 2024
Reviewer Name / DateKenneth Mosman, July 12, 2024