Skip to content

Daily Field Report

Date :04/23/2024
Project No :2023C180
Client Company :Artisan Communities
Arrival Time :04/23/2024 10:30
Onsite Hours :07:00
Name of the Project :Lakeside Sub. - Lovers Lane, Calhoun
Project Location :Calhoun
Weather :sunny
Departure Time :04/23/2024 17:30
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

  • The placement and compaction of fill soils for the sewer trench between SSMH 4.3 to SSMH 6.1 and installing sewer pipe between SSMH6.1 and SSMH 6.2, continued this day.
  • At the time of arrival, our representative observed that work was in progress with 1-foot lifts being placed and compacted using 810F compaction equipment along with general probing using a 3/8″ diameter probe rod.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateAminullah Azimi, April 23, 2024
Reviewer Name / DateKenneth Mosman, May 23, 2024