Density Test Report

Date :04/19/2024
Project No :2022C106
Client Company :CWM
Arrival Time :04/19/2024 10:30
Onsite Hours :07:30
Name of the Project :Taxiway 2022 Pavement Replacement
Project Location :HJAIA
Weather :sunny
Departure Time :04/19/2024 18:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
04/19/2024 1 4 134.2 GAB 1 135.6 6.8 99.0 95 D6938 Pass
Location : 76 feet north of purposed NLVR, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
04/19/2024 2 4.3 130.5 GAB 1 135.6 6.8 96.2 95 D6938 Pass
Location : 31 feet north of NLVR, Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
04/19/2024 3 4.6 131.5 GAB 1 135.6 6.8 97.0 95 D6938 Pass
Location : 15 feet south of NLVR , Elv/Depth :finished grade
Comment : Gauge Serial No. :85759
Technician Signature / DateAminullah Azimi, April 19, 2024
Reviewer Name / DateKenneth Mosman, May 23, 2024