- Home
- Daily Field Report Report ID: 63509
- This project is inactive from admin.Download Report
Daily Field Report
Date :12/22/2023
Project No :2023C141
Client Company :Toll Bros
Arrival Time :12/22/2023 12:00
Onsite Hours :02:00
Name of the Project :N. Gate - Old Atlanta Road
Project Location :Cumming
Weather :sunny
Departure Time :12/22/2023 14:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
- A footing evaluation was performed by visual inspection and probing for the culvert footing,
- During the evaluation, some soft soils were encountered. We recommended the removal of up to 4 feet of these unsuitable soils to reach suitable residual soils.
Technician Signature / DateAminullah Azimi, December 22, 2023
Reviewer Name / DateKenneth Mosman, March 09, 2024