- Density Test Report Report ID: 63323
- This project is inactive from admin.Download Report
Density Test Report
Date :12/13/2023
Project No :2023C195
Client Company :Toll Bros. Inc.
Arrival Time :12/13/2023 14:00
Onsite Hours :03:00
Name of the Project :Kimbal Bridge Tract
Project Location :Alpharetta
Weather :sunny
Departure Time :12/13/2023 17:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
---|---|---|---|---|---|---|---|---|---|---|
12/13/2023 | 1 | 15.3 | 108.1 | 24209 | 111.6 | 16.5 | 96.9 | 95 | D6938 | Pass |
Location : | 63 feet to east of MH 9I, Elv/Depth :finished grade | |||||||||
Comment : | Gauge Serial No. :85759 | |||||||||
12/13/2023 | 2 | 17.1 | 108.0 | 24209 | 111.6 | 16.5 | 96.8 | 95 | D6938 | Pass |
Location : | 34 feet to west of MH 9H, Elv/Depth :finished grade | |||||||||
Comment : | Gauge Serial No. :85759 |
Technician Signature / DateAminullah Azimi, December 13, 2023
Reviewer Name / DateKenneth Mosman, March 09, 2024