Density Test Report

Date :08/31/2023
Project No :2022C235
Client Company :Jackson Demolition Service, Inc.
Arrival Time :08/31/2023 06:00
Onsite Hours :10:30
Name of the Project :Plant Gorgas Demolition and Grading
Project Location :460 Gorgas Rd, Parrish, AL 35580
Weather :SUNNY
Departure Time :08/31/2023 16:30
ASEC Technician Name :Avinash Bandham

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
08/31/2023 4 15.4 109.5 ASEC-2 110.9 15.3 Check
Location : Section 2 basement area G7, Elv/Depth :274
Comment :
08/31/2023 1 15.4 106.6 ASEC-2 110.9 15.3 96.1 95 D6938 Pass
Location : Section 1 basement area B7, Elv/Depth :274
Comment : Gauge Serial No. :30942
08/31/2023 2 16.5 107.0 ASEC-2 110.9 15.3 96.5 95 D6938 Pass
Location : Section 2 basement area G7, Elv/Depth :274
Comment : Gauge Serial No. :30942
08/31/2023 3 16.8 106.8 ASEC-2 110.9 15.3 96.3 95 D6938 Pass
Location : Section 2 basement area G7, Elv/Depth :274
Comment : Gauge Serial No. :30942
Technician Signature / DateAvinash Bandham, August 31, 2023
Reviewer Name / DateRamchandra Mogulla, September 15, 2023