- Home
- Daily Field Report Report ID: 60450
- This project is inactive from admin.Download Report
Daily Field Report
Date :07/22/2023
Project No :2022C178
Client Company :CW Matthews
Arrival Time :07/22/2023 11:00
Onsite Hours :06:00
Name of the Project :Ramp 2 Pavement Replacement
Project Location :HJAIA
Weather :sunny
Departure Time :07/22/2023 17:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
At the request of the client’s representative, our AS ENGINEERING AND CONSULTING, LLC (ASEC) representative visited the job site to observe the contractor’s work activities from a quality standpoint to assure compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site this shift:
- A pre-pour observation was performed in the Ramp 2, phase 10, Lane 1 and Lane 3 and lane 5, portions of the project this day. The contractor completed rebar and dowel basket placement for these lanes.
- The writer visually inspected the installation and setup of these lanes and advised the contractor representatives of any minor corrections that were required.
- Contractor cleaned loose rock and debris and puddles of water from the base.
- Baskets were found to be level and straight and secured.
- Dowel bars have epoxy. Embedment depth was found to be 15″ in concrete.
- Our representative along with Thomas of ATLQA and the ATLNext representative Craig and CWM rep Brandon signed the pre-pour card.
Technician Signature / DateAminullah Azimi, July 22, 2023
Reviewer Name / DateKenneth Mosman, July 30, 2023