- Home
- Daily Field Report Report ID: 59471
- This project is inactive from admin.Download Report
Daily Field Report
Date :05/26/2023
Project No :2023C136
Client Company :Excellere
Arrival Time :05/26/2023 8:00
Onsite Hours :9:30
Name of the Project :Big Creek Boardwalks
Project Location :Alpharetta
Weather :sunny
Departure Time :05/26/2023 17:30
ASEC Technician Name :Aminullah Azimi
Observations/Finding
At the request of the client’s representative, AS ENGINEERING AND CONSULTING, LLC (ASEC) representative, Amin Azimi visited the job site to observe and monitor the contractor’s work activities from a quality standpoint to assure compliance with project drawings/specifications, applicable codes, and materials submittals and conducted QC testing per the project drawings and specifications. The following observations were made on site this shift:
Our representative performed observation of drilling and installation of Helical piles and documented the results. Results are attached in a separate report.
Technician Signature / DateAminullah Azimi, May 26, 2023
Reviewer Name / DateKenneth Mosman, July 08, 2023