Density Test Report
Date :05/17/2023
Project No :2022C113
Client Company :CWM
Arrival Time :05/17/2023 10:00
Onsite Hours :08:00
Name of the Project :Airfield Sewer Enhancements
Project Location :HJAIA
Weather :cloudy
Departure Time :05/17/2023 18:00
ASEC Technician Name :Aminullah Azimi
Observations/Finding
Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
---|---|---|---|---|---|---|---|---|---|---|
05/17/2023 | 1 | 3.3 | 134.8 | GAB 23411 | 140.2 | 5.7 | 96.1 | 90 | D6938 | Pass |
Location : | 40 feet to west of MH1, Elv/Depth :- 1.5 foot | |||||||||
Comment : | Test result standby for proctor | Gauge Serial No. :85759 | ||||||||
05/17/2023 | 2 | 3.5 | 134.8 | GAB 23411 | 140.2 | 5.7 | 96.1 | 90 | D6938 | Pass |
Location : | 39 feet to west of MH2, Elv/Depth :8 inches below finish grade | |||||||||
Comment : | test result standby for proctor | Gauge Serial No. :85759 | ||||||||
05/17/2023 | 3 | 4.5 | 136.9 | GAB 23411 | 140.2 | 5.7 | 97.6 | 90 | D6938 | Pass |
Location : | 17 feet to west of MH1, Elv/Depth :at finish grade | |||||||||
Comment : | test result on standby for proctor | Gauge Serial No. :85759 | ||||||||
05/17/2023 | 4 | 5.9 | 124.9 | GAB 23411 | 140.2 | 5.7 | 89.1 | 90 | D6938 | Fail |
Location : | 45 feet to North of MH2, Elv/Depth :1 foot below finish grade | |||||||||
Comment : | test result on standby for proctor | Gauge Serial No. :85759 | ||||||||
05/17/2023 | 5 | 6.6 | 122.6 | Recycled GAB | 134.9 | 8.7 | 90.9 | 90 | D6938 | Pass |
Location : | 25 feet to South of MH3, Elv/Depth :1 foot below finish grade | |||||||||
Comment : | Gauge Serial No. :85759 |
Technician Signature / DateAminullah Azimi, May 17, 2023
Reviewer Name / DateRamchandra Mogulla, July 10, 2023