Daily Field Report

Date :05/09/2023
Project No :2022C113
Client Company :CWM
Arrival Time :05/09/2023 12:00
Onsite Hours :04:00
Name of the Project :Airfield Sewer Enhancements
Project Location :HJAIA
Weather :sunny
Departure Time :05/09/2023 16:00
ASEC Technician Name :Aminullah Azimi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services, visual observation techniques were employed to assure compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

The placement and compaction of backfill soils for the water storm pipe trench between manholes, MH#1 to MH#2 continued this day.

At the time of arrival, our representative observed that work was in progress with lifts being placed at about 4 feet below finished grade and compacted using a  16 ton smooth drum compactor.

Note: compacted materials (a mixture of piedmont soils and graded aggregate base) test results are on standby until a moisture-density relationship (proctor) can be performed.

See attached photos.

Technician Signature / DateAminullah Azimi, May 9, 2023
Reviewer Name / DateKenneth Mosman, July 08, 2023