Skip to content

Daily Field Report

Date :04/29/2023
Project No :2022C235
Client Company :Jackson Demolition Service, Inc.
Arrival Time :04/29/2023 06:00
Onsite Hours :10:30
Name of the Project :Plant Gorgas Demolition and Grading
Project Location :460 Gorgas Rd, Parrish, AL 35580
Weather :SUNNY
Departure Time :04/29/2023 16:30
ASEC Technician Name :Avinash Bandham

Observations/Finding

AS ENGINEERING AND CONSULTING, LLC (ASEC) representative Avinash Bandam visited the site at the request of Jackson Demolition representative Josh Kelly. The undersigned representative was present to monitor, verify and document the ongoing project activities. (reference drawing E720661 S1 – R5, E720659 S1-R5.)

During the visit, the following observations were made:

  1. Two thousand (2394) cubic yards of fill materials were received and placed for lift (7) in section 2 basement area G7 (drawing E720661) of the basement. The materials were placed and compacted in compliance with ITP-001.

2394 cub. Yds of fill material were placed

compacting the section-2 basement area G7 using the roller and dozer.

Technician Signature / DateAvinash Bandham, April 29, 2023
Reviewer Name / DateRamchandra Mogulla, May 05, 2023