- Daily Field Report Report ID: 58300
- This project is inactive from admin.Download Report
Daily Field Report
Date :10/22/2021
Project No :2021C073
Client Company :DR Horton West
Arrival Time :10/22/2021 09:00
Onsite Hours :9:30
Name of the Project :Tributary C2A
Project Location :Riverside Parkway, City of Douglasville, GA
Weather :Partly Cloudy
Departure Time :10/22/2021 18:30
ASEC Technician Name :Christopher Burrow II
Observations/Finding
The undersigned ASEC Inspector was on site, on the above date, visited the job site to observe and monitor the contractor’s work activities, and also conduct necessary testing for acceptance. The following observations were made, and required testing was performed in accordance with project specifications.
The following are observations that were made at this time:
- Excavation, pipe installation and backfilling continued along the sanitary sewer lines between manholes S0 and S1.
- Approximately 180 feet of 8 in PVC pipe was installed along this line to complete this section of the alignment.
- Based on review of guidelines for fill placement, the required compaction for structural fill at the above mentioned area was 95 % of standard proctor.
- Based on visual observation and field measuring, the fill was placed in 8 to 12 inch thick lifts and compacted using a CAT CP44b sheepsfoot compactor (weight; 16,471 lbs.). Based on density testing, the fill placed today at depths between approximately -12 feet and 0 feet below finished grade was compacted according to fill placement guidelines.
- Moisture content of the excavated material appeared to be on the wetter side.
- Please find the corresponding density test report for this day for test results.
ASEC recommends sealing of the surface of placed fill from inclement weather and to maintain positive drainage.
The contractor was notified about results.
Technician Signature / DateChristopher Burrow II, October 22, 2021
Reviewer Name / DateRamchandra Mogulla, April 03, 2023