Daily Field Report

Date :03/04/2022
Project No :2021C078
Client Company :CCG Constructors LLC (Century)
Arrival Time :03/04/2022
Onsite Hours :
Name of the Project :Pickens Landing Development
Project Location :Dacula, GA
Weather :75 sunny
Departure Time :03/04/2022
ASEC Technician Name :Russell Hendrix

Observations/Finding

The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals. The following observations were made on site today:

A meeting was held with Chris Bray, superintendent for Charles Pruitte, Inc in regard to the excavation located near the pump station at the X9 manhole.   Rock was discovered in an area that measured to be approximately 10 feet x 30 feet x 4 feet in depth.  An excavator with a hammer would be required to remove these materials.

Fill lifts were started on Pickens Landing drive from Sta 1+25 to 2+75 (Lots #1 & 2).  Lifts were placed between 10 to 13 inches in thickness.  A discussion with Brad the grading foreman was initiated about lift sizes.  The soil types were a mix with a small amount of organic material.  Please see attached density tests.

Technician Signature / DateRussell Hendrix, March 4, 2022
Reviewer Name / DateRamchandra Mogulla, December 12, 2022