Daily Field Report

Date :11/16/2021
Project No :2021C074
Client Company :DR Horton West
Arrival Time :11/16/2021 10:30
Onsite Hours :06:00
Name of the Project :Oakhurst Glen - Ph 4
Project Location :Mallord Drive, South Fulton, GA
Weather :Partly cloudy
Departure Time :11/16/2021 16:30
ASEC Technician Name :Christopher Burrow II

Observations/Finding

The undersigned ASEC Inspector was on site, on the above date, for the purpose of general site monitoring and assessment of contractor and subcontractor activities. The following are observations that were made at this time:

-Continued pipe laying in the approximate area of manhole 5.8.

-Rock Breaking continued on site.

-Continued moving rocks into pits to clear them off of lot and fill areas.

-Shaping fill slopes on perimeter of site area.

-Precision blasting on site for rock blasting.

Technician Signature / DateChristopher Burrow II, November 16, 2021
Reviewer Name / DateKenneth Mosman, December 06, 2021