Daily Field Report
Date :11/12/2021
Project No :2020C007
Client Company :Pulte Group
Arrival Time :11/03/2021 07:00
Onsite Hours :00:30
Name of the Project :Winslow at Brookstone
Project Location :6156 Collins Road, Acworth, GA 30101
Weather :
Departure Time :11/03/2021 07:30
ASEC Technician Name :Russell Hendrix
Observations/Finding
The site was visited by the undersigned AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to assure compliance with project drawings/specifications, applicable codes, and materials submittals.
A slab inspection for Lot #25 at Winslow was conducted for the preparation of concrete placement. No DCPs were completed as the slab had all wire & saddles placed and was covered with vapor barrier and stone.
Technician Signature / DateRussell Hendrix, November 12, 2021
Reviewer Name / DateKenneth Mosman, December 15, 2021