- Density Test Report Report ID: 34248
- This project is inactive from admin.Download Report
Density Test Report
Date :10/25/2021
Project No :2021C070
Client Company :CCG Constructors LLC (Century)
Arrival Time :10/25/2021 02:00
Onsite Hours :03:00
Name of the Project :Harmony Heights
Project Location :Mt. Olive Road at Brentwood Drive, Commerce, GA
Weather :cloudy
Departure Time :10/25/2021 05:00
ASEC Technician Name :Russell Hendrix
Observations/Finding
Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
---|---|---|---|---|---|---|---|---|---|---|
10/25/2021 | 1 | 20.8 | 96.9 | P-01 | 102.0 | 16.6 | 95.0 | 95 | D6938 | Fail |
Location : | Lot 121-Lot 122, Elv/Depth :900 | |||||||||
Comment : | Gauge Serial No. :30942 | |||||||||
10/25/2021 | 2 | 18.6 | 102.1 | P-02 | 105.6 | 16.6 | 96.7 | 95 | D6938 | Pass |
Location : | Lots 121-Lots 122, Elv/Depth :900 | |||||||||
Comment : | Had discussion with Foreman. additional compacting was done. | Gauge Serial No. :30942 | ||||||||
10/25/2021 | 3 (retest of 1&2) | 18.9 | 103.6 | P-02 | 105.6 | 16.6 | 98.1 | 95 | D6938 | Pass |
Location : | Lots 121-122, Elv/Depth :900 | |||||||||
Comment : | Pass after continued compaction. | Gauge Serial No. :30942 |
Technician Signature / DateRussell Hendrix, October 25, 2021
Reviewer Name / DateRamchandra Mogulla, November 18, 2021